{6} All Tickets By Milestone (Including closed) (8 matches)

A more complex example to show how to make advanced reports.

1.0 (8 matches)

Ticket Summary Component Status Resolution Version Type Priority Owner Modified
#8 Prepare first release general closed fixed 1.0dev task normal tangm 07/07/18
#7 Implements CSNS Zip Mapper Interface general closed fixed 1.0dev task normal tangm 07/06/18
#6 Implements IDS main storage interface for iRODS general closed fixed 1.0dev task normal tangm 07/06/18
#5 Add .gitignore general closed fixed 1.0dev task low tangm 05/26/18
#4 Create Maven project general closed fixed 1.0dev task highest tangm 05/26/18
#3 Setup Jenkin job general closed fixed 1.0dev task highest tangm 05/26/18
#2 Setup Gerrit general closed fixed 1.0dev task highest tangm 05/26/18
#1 Setup Trac general closed fixed 1.0dev defect high tangm 05/26/18
Note: See TracReports for help on using and creating reports.